GIRS accredited gas diversion specialists

Gas Diversions & Relocations

Permanent and temporary gas main diversions for developers, highways authorities, and principal contractors. Full GDN approval management and safe dig capability.

GIRS accredited Safe dig capability GDN managed
The Process
1
Asset location & survey
2
GDN agreement & design
3
Installation & decommissioning
4
Testing & adoption
From Survey to Adoption

The Process Step by Step

Every gas diversion follows a clear, auditable sequence. Here is exactly what happens at each stage.

1

Asset Location and Survey

Before any diversion design work can begin, the precise location, depth, and condition of the existing gas main must be established. USP carries out a desk study using GDN records, followed by electromagnetic detection surveys and, where the ground conditions or pipe proximity warrant it, vacuum excavation (suction excavation) to expose the pipe without risk of damage. Accurate as-found data at this stage is critical. Errors in assumed pipe position can cause abortive design work, programme delays, and in the worst case, unsafe working conditions on site.

2

GDN Agreement and Design Approval

A gas main diversion cannot proceed without a formal agreement with the GDN. USP prepares the diversion application, including the proposed new route, pipe size, material specification, and method of connection to the existing network. The GDN reviews the application, carries out its own network analysis, and issues an agreement setting out the non-contestable charges and technical requirements. Where the diversion crosses a public highway, NRSWA Section 50 or Section 171 licences may also be required. USP manages both the GDN agreement and the highways approval processes in parallel to protect the programme.

3

Installation and Decommissioning

With GDN agreement and design approval in place, USP mobilises its GIRS-accredited installation team to install the new pipe route. All new pipework is electrofusion jointed, pressure tested in accordance with IGE/TD/3, and inspected before the GDN carries out the non-contestable live connection. Once the new route is live and supply has transferred, the redundant section of main is purged, decommissioned, and either left in situ (capped and recorded) or removed where the site conditions require it. All as-built drawings and pressure test records are submitted to the GDN as part of the adoption package.

4

Temporary Diversions

On sites where continuous gas supply must be maintained during construction of the permanent diversion route, USP designs and installs a temporary above-ground pipeline to bridge the gap. Temporary pipelines are designed to GDN technical standards, require formal approval before installation, and are managed with the same rigour as permanent works. USP coordinates the cutover from temporary to permanent supply with minimum disruption to affected properties and integrates this with the overall construction programme.

Key Technical Considerations

Technical Specifications

The critical parameters that govern every gas main diversion and relocation.

When required
Building over an existing main, new road conflicts, site redevelopment, highway schemes, Section 104 drainage, and major infrastructure projects.
Approval
GDN formal agreement required before any diversion work commences. No approval, no work. USP manages this process from initial application to agreement issue.
Non-contestable
GDN carries out all tapping and live main connections. These are outside USP's scope but are coordinated closely with the contestable programme.
Contestable
USP installs the new pipe route, civil works, electrofusion jointing, pressure testing, and decommissioning of the redundant section.
Reinstatement
Old pipe purged and decommissioned or removed. All reinstatement carried out to highway authority standards where applicable.
Highway works
NRSWA approvals required for diversions crossing or running within public highways. USP manages Section 50 licences and traffic management coordination.
Why Choose USP

What USP Can Do For You

End-to-end capability from a single GIRS-accredited provider.

GIRS accredited for gas main diversions. USP is authorised by Cadent Gas and approved by Lloyd's Register for contestable diversion works.
Full GDN approval management from initial application through to formal agreement, including technical submissions and programme coordination.
Safe dig and vacuum excavation capability for precise asset location without risk of damage to live gas infrastructure.
Coordinate gas diversions with water main and electrical diversions on the same programme, reducing programme risk and civils cost.
Integrate seamlessly with the principal contractor's overall site programme, providing a single point of contact for all utility diversion matters.
Certified Provider

Fully Accredited & Committed to Safety

Every gas diversion we deliver meets the highest industry standards. Worker safety, public safety, environmental responsibility, and project compliance from planning to sign-off.

WaterSafe accredited
WIAPS accredited
LRQA WIRS certified
LRQA NERS certified
LRQA GIRS certified
ISO 9001 certified
Achilles UVDB Silver Plus
Constructionline member
SSIP accredited
Acclaim accredited
What Our Clients Say About Us

Rated 5.0 ★★★★★

50 Google Reviews

Gas Diversions FAQs

Frequently Asked Questions

A gas main diversion is required whenever a proposed development or highway scheme conflicts with an existing gas main. Common triggers include building over or close to an existing main (which is not permitted under standard GDN conditions), road realignment or new junction works, site redevelopment where existing mains cross the footprint of proposed buildings, Section 104 drainage schemes, and major infrastructure projects. The GDN asset records must be checked at the earliest feasibility stage to identify any conflicts.
Live main connections, including the tapping of the existing main and the isolation and purging of the section to be decommissioned, are non-contestable works. They must be carried out by the GDN under its own programme. USP manages the coordination between the GDN non-contestable programme and the contestable new pipe route installation to avoid delays and gaps in the works sequence.
The GDN formal agreement process typically takes 8 to 16 weeks from initial application, depending on the complexity of the diversion, the network analysis required, and the GDN's current workload. Where highway approvals are also needed, additional time must be allowed for NRSWA notices and any traffic management agreements. USP initiates the process as early as possible in the project programme to avoid critical path delays.
Yes. Where a gas main must remain live during the construction of the permanent diversion route, a temporary above-ground pipeline can be designed and installed to maintain supply to affected properties. Temporary pipelines require their own design approval from the GDN and must be managed carefully to ensure continuous supply. USP has experience in designing and managing temporary gas diversion arrangements on complex sites.
Yes. Multi-utility diversion coordination is one of USP's core capabilities. By acting as the single point of contact for gas, water, and electrical diversions on the same programme, USP aligns GDN, water company, and DNO programmes, identifies shared trench opportunities, and integrates with the principal contractor's overall site programme. This significantly reduces the risk of sequential delays and abortive civils costs.
Get Started

Need a Gas Main
Diverted on Your Site?

Tell us about your project and we will send you a free, no-obligation diversion assessment within 24 hours.

100% free, no obligation Response within 24 hours 5.0 from 50 Google reviews

Prefer to talk? Call 024 7542 6505 for immediate service.

Get a Quote