Article By Utility Solutions Provider Team 6 min read

Water Diversions on Construction Sites: Rules and Process

A water diversion is the process of moving an existing water main or service to accommodate new construction, highway works, or ground-level changes. They are common on commercial and infrastructure and transport projects, and they are one of the most time-sensitive items on a construction programme because water company lead times are long and the works must not disrupt supply to existing customers.

This guide explains how water diversions work in the UK, what they cost, and how to plan them.

When a Water Diversion Is Needed

A diversion is required when a proposed new structure or excavation clashes with an existing water main or service. Triggers include:

New building footprints crossing existing mains.

Foundation or piling works within the exclusion zone of a main.

Highway realignment or new road crossings.

Ground-level changes that would reduce the cover depth above a main.

New utilities being installed that cannot clear the existing main route.

Demolition of existing buildings served by mains that would remain in use after the demolition, which often also needs careful disconnection and alteration planning.

The first warning sign is usually a statutory utility search or a GPR survey showing a main in or near the proposed works.

Who Owns the Asset

Diversions are controlled by the asset owner. For most water mains, this is the local water company (Thames Water, Severn Trent, Anglian Water, etc.). For some private estates and industrial sites, the main may be owned by the site operator. For sewers, ownership may lie with the sewerage undertaker (usually the same as the water company) or with the developer if the sewer has not been adopted.

The asset owner has the final say on design and execution. They will not allow a third party to touch the main directly.

Cost Drivers

Water diversion costs range from a few thousand pounds for a short, low-pressure diversion to several hundred thousand pounds for a long, large-diameter diversion on a busy road.

Main cost drivers:

Length of diversion. Longer routes mean more excavation and more pipe.

Pipe diameter and material. Larger mains cost more per metre to divert. Ductile iron and asbestos cement mains require specific handling.

Pressure tier. High-pressure distribution mains are more complex than low-pressure distribution.

Traffic management. Road closures on busy routes add significant cost.

Ground conditions. Hard ground, shallow bedrock, or contamination increase civils cost.

Interface with other services. Clashes with gas, electricity, or telecoms add survey and coordination cost, particularly alongside gas diversions on construction projects.

Disinfection and testing. All new main sections require pressure testing and bacteriological clearance.

Customer connections affected. If existing customers are on the main being diverted, their services may also need diversion or temporary supply arrangements.

Typical Timeline

Water diversion timelines are long. Typical phases:

Initial enquiry and site visit: two to four weeks.

Feasibility study and budget quote: four to eight weeks.

Detailed design and water company approval: eight to sixteen weeks.

Programming and customer notifications: four to eight weeks.

On-site works: two to eight weeks depending on scope.

Pressure testing and bacteriological clearance: two to three weeks.

Tie-in and commissioning: one to two weeks.

Total elapsed time: six to twelve months from first enquiry to completion.

Complex diversions with multiple customer impacts can extend to eighteen months.

Asbestos Cement Mains

A significant portion of the UK water main network is still asbestos cement, installed from the 1950s through the 1980s. Any diversion of an AC main triggers specific handling requirements:

Controlled excavation with dust suppression.

HSE-licensed asbestos contractors for pipe removal.

Disposal as hazardous waste.

Enhanced PPE and monitoring.

These requirements add to both cost and programme. Budget an extra 20 to 40 per cent on cost and two to four weeks on programme for AC diversions.

Temporary Supply and Customer Impact

Many water diversions affect customer supplies. Options for managing this include:

Overnight shut-offs with advance notification, for diversions that can complete a new connection within hours.

Temporary supplies from bowsers or overland pipes for longer shut-offs.

Temporary network reconfiguration to feed affected customers from another direction.

Each option has cost and regulatory implications. Customer notification must comply with the water company’s customer service standards.

Cost Recovery

Water diversions are generally paid for by the requesting party (the developer or highway authority). Ofwat’s charging rules allow the water company to recover its reasonable costs from the requesting party, with limited exceptions for certain statutory schemes.

Assume the diversion is 100 per cent your cost unless a specific statutory exception applies.

How to Reduce the Pain

Identify water assets at the feasibility stage, before building layouts are frozen.

Design to avoid where possible. A main that can be left in place with a suitable setback is much cheaper than a diversion.

Engage the water company as early as possible. Their design and programme lead times are the binding constraint.

Coordinate with other utility diversions on construction sites to share traffic management and civils.

Consider temporary-then-permanent diversions on constrained sites, where a temporary diversion allows construction to proceed and the permanent diversion is done during a later programme phase.

What Good Looks Like

A well-managed water diversion is identified at RIBA stage 2 or 3, quoted by stage 3 or 4, designed and approved by stage 4 or 5, and executed before the building works reach the critical point of conflict. Customer impact is minimised through planned, notified shut-offs. Documentation is complete on handover.

Done badly, the diversion is identified during construction, the water company’s lead time exceeds the available window, and the project either pauses or the building design is reworked around the main at significant cost.

The Bottom Line

Water diversions are slow, expensive, and tightly controlled. The only way to manage them is early identification and long lead times. Built into the programme from the start, they are manageable. Discovered at the last minute, they can become project-threatening. If you think your scheme might need one, it is worth getting a quote at feasibility stage rather than after design freeze.

Ready to start your project?

Get a free, no-obligation quote from USP. One PM, one contract, weekly updates.

Get a free quote

Related posts

Get a free quote